Rule 4
Application To Be Submitted To Obtain A License To Conduct A Survey Of Production Of Electricity

Any person or corporate body who is interested  to conduct a survey of production of electricity shall have to submit an  application in triplicate (three copies) stating the following particulars
relating to the proposed electricity production project to the Secretary  through the Electricity Development Department in the format as prescribed  in Schedule- 2:-
(a) Map of the project-site (in which preliminary sketch of the proposed  power-house, dam, reservoir, canal, tunnel, sub-station, transmission  line, and village, town, historical places, way etc. inside the project site  also should be clearly shown),
(b) Area of water-resources to be surveyed and quantity of water to be  utilized,
(c) Estimated amount of cost and time for the completion of project (both  the survey and construction),
(d) Total capacity of the project and estimate of annual production,
(e) In case the electricity is to be produced through other means except  other than water resources, types of fuel and method of acquiring the  fuel should be mentioned,
(f) Other necessary matters.