Rule 4
Application To Be Submitted To Obtain A License To Conduct A Survey Of Production Of Electricity
–
Any person or corporate body who is interested to conduct a survey of production of electricity shall have to submit an application in triplicate (three copies) stating the following particulars
relating to the proposed electricity production project to the Secretary through the Electricity Development Department in the format as prescribed in Schedule- 2:-
(a) Map of the project-site (in which preliminary sketch of the proposed power-house, dam, reservoir, canal, tunnel, sub-station, transmission line, and village, town, historical places, way etc. inside the project site also should be clearly shown),
(b) Area of water-resources to be surveyed and quantity of water to be utilized,
(c) Estimated amount of cost and time for the completion of project (both the survey and construction),
(d) Total capacity of the project and estimate of annual production,
(e) In case the electricity is to be produced through other means except other than water resources, types of fuel and method of acquiring the fuel should be mentioned,
(f) Other necessary matters.
Any person or corporate body who is interested to conduct a survey of production of electricity shall have to submit an application in triplicate (three copies) stating the following particulars
relating to the proposed electricity production project to the Secretary through the Electricity Development Department in the format as prescribed in Schedule- 2:-
(a) Map of the project-site (in which preliminary sketch of the proposed power-house, dam, reservoir, canal, tunnel, sub-station, transmission line, and village, town, historical places, way etc. inside the project site also should be clearly shown),
(b) Area of water-resources to be surveyed and quantity of water to be utilized,
(c) Estimated amount of cost and time for the completion of project (both the survey and construction),
(d) Total capacity of the project and estimate of annual production,
(e) In case the electricity is to be produced through other means except other than water resources, types of fuel and method of acquiring the fuel should be mentioned,
(f) Other necessary matters.